  • 2814 Isleville weekly update.

  • North Park Street Upgrades.

  • Harris East securing the neighbours.

  • Slowly but surely Q Lofts is coming together

  • 3065 Robie weekly update.

  • Exterior clading going up on The Albro at Avonhurst Gardens.

  • The Avery.

  • King’s Wharf.

  • Brunswick Street commercial addition at Duke Street.

  • The Mary-Anne.

  • 5504 Spring Garden Road.

  • Collaborative Health Education Centre at Dalhousie.

  • 2814 Isleville weekly update. Not sure if it was plumbing or electrical but there was piping being encased in concrete. The future mechanical room is where the piping leads to.

  • Fencing is up for the demolition of 3138 Isleville.

  • 3065 Robie weekly update. 

  • Q Lofts

  • Harris East weekly update. Excavation continues at a brisk pace. With only one floor underground and small building footprint it shouldn’t be long before we see concrete trucks!

  • In my opinion 6009-6017 Quinpool & 2032-2050 Robie will make the Commons backdrop much more attractive. Agree or disagree make sure to tell HRM through the online survey or at the open house October 1st. 

  • 2814 Isleville weekly update.

  • 3065 Robie working on the elevator shaft and parkade lobby.

  • HALIFAX DEVELOPMENTS MAP

    The Halifax Developments Map has been updated with new renderings from W.M. Fares Group (http://www.wmfares.com/)! Roberts & Maynard is a new proposal consisting of a 7 storey (+ penthouse) residential building and ground floor retail for the vacant lot across from Q Lofts. The Wallis was introduced to the Design Review Committee earlier this summer.…

  • Harris East works better than alarm clocks at 7am!

  • 2814 Isleville. Work continues on the interior walls forming the future parkade lobby. The elevator shaft can easily been seen. The half wall has been poured underneath the future parkade access ramp (see outline on right). 

  • 3065 Robie weekly update

  • Cladding going up along Roberts Street at the Q Lofts.